SAMPLE
BuildBrief logoBuildBrief
WEEKLY PROGRESS REPORT

Cedar Rapids Data Center Campus — Building 1

Cedar Rapids, Iowa · Weekly visual documentation by BuildBrief
Report WeekWeek 24 of 96
Capture DateTue, Aug 11, 2026
DeliveredFri, Aug 14 · 4:02 PM
Weather StationKCID · Cedar Rapids, 4.2 mi
Prepared ForProject Owner / Development Team
buildbrief.com · hello@getbuildbrief.com · (321) 710-9671 · Demonstration report — representative content

This Week at a Glance

31%Overall Complete▲ +1.5% this week
6Milestones Completed
1Weather Delay−4 hrs, recovered
58Photos Archived
Overall progress — actual vs. planned31% actual · 30% planned · ahead of schedule

The project remains approximately one week ahead of the baseline schedule. Tuesday's lightning hold cost 4 hours and was recovered with Thursday's extended shift at no premium cost. No budget flags this week.

BuildBrief · Weekly Progress Report · Week 24 · SAMPLE

Weather Log — Site Conditions This Week

☀️
Mon88°F · Clear
Full shift
⛈️
Tue84°F · Storms
−4 hrs · AM lightning hold
⛅
Wed86°F · Partly cloudy
Full shift
☀️
Thu91°F · Clear
Extended shift +2 hrs
☀️
Fri89°F · Clear
Full shift
Weather is logged weekly to document conditions for schedule records and any future delay analysis. Source: on-site observation plus the nearest reporting station. This week's single weather event (Tuesday AM lightning hold) was fully recovered within the same week.
BuildBrief · Weekly Progress Report · Week 24 · SAMPLE

Manning On Site — Trade Count This Week

Trade / ContractorTueWedThuFriSatStatus
Steel erection — Ironbridge Steel14141616—On plan
Concrete — Summit Concrete9116——On plan
Electrical — Beacon Electric6688—On plan
Site fencing — Perimeter Fence Co.44———Complete
Plumbing / FP — Twin City Mechanical3355—On plan
Earthwork / utilities — Heartland Excavating—5555Sat shift
Total on site364340345GC staff: 4 daily

Photo Documentation — Week 24

Aerial overview of site
P01 — Site Overview, NorthOverall site status · Aug 11, 9:12 AM · fixed weekly angle
Steel and crane progress
P02 — Steel & Crane, Zone BErection through gridline B6 · Aug 11, 9:20 AM
Rebar cage progress
P03 — Rebar Cage, Grid B4Data Hall 1 north row · Aug 11, 9:31 AM
West elevation frame
P04 — Frame, West ElevationWest elevation framing · Aug 11, 9:44 AM
BuildBrief · Weekly Progress Report · Week 24 · SAMPLE

Progress in Motion — Last 5 Weeks, Same Angle

Week 20
WEEK 20
Week 21
WEEK 21
Week 22
WEEK 22
Week 23
WEEK 23
Week 24 — this week
WEEK 24 · NOW

The same fixed aerial position, every week — progress is directly comparable week over week. Your full week-by-week sequence, from groundbreaking to today, lives in your project archive.

Current week, fixed position A01
Current week — fixed position A01

Zone B steel progression is visible W20 → W24. The full weekly sequence (W01–W24) is filed in the project archive, searchable by date and zone.

BuildBrief · Weekly Progress Report · Week 24 · SAMPLE

This Month's Executive Video

▶ Click on the video to play
Sample Clip
Month 6 Progress Film — sample clip (0:17)

This is where your finished monthly film plays inside the report — flyovers, month-over-month progress, and milestone captions.

Live delivery is a polished 3–5 minute edit; this demo uses licensed stock footage.

Archive ref: BB-CR1 / FILM-006
Suitable for investor distribution as delivered
BuildBrief · Weekly Progress Report · Week 24 · SAMPLE

Work Completed This Week

  • Structural steel erection completed through gridline B6 (Zone B, frames 12–18)
  • Data Hall 1 slab-on-grade pour finished — 44,000 sq ft, curing blankets removed
  • Overhead electrical cable tray installed, Data Hall 1 north row (60% of row complete)
  • Transformer pads 3 & 4 poured and anchored, south yard
  • Perimeter security fencing completed along east property line (1,900 LF)
  • Chilled-water pipe racks set to elevation, mechanical yard

Scheduled Next Week (Aug 17–21)

  • Steel erection continues — Zone B frames 19–24; crane pick plan #9 in effect
  • Data Hall 1 roof deck installation begins Tuesday
  • Generator 1 & 2 delivery and set (Wednesday, road closure notice issued)
  • Underground storm drainage tie-in at south yard, phase 2 of 3
  • Fire-protection main pressure test, Data Hall 1
BuildBrief · Weekly Progress Report · Week 24 · SAMPLE

Decisions Needed From You

Confirm final CRAC unit layout revision (Rev 3 drawing issued Aug 7)Holds mechanical rough-in start in Data Hall 2 — ~5 working days at risk
Due Aug 19
Approve generator enclosure color/finish selectionNo current schedule impact; long-lead paint order follows approval
Due Aug 28

Site Watch — What We Noticed

Two subcontractor crews observed without visible fall-protection anchors, Zone B — flagged to GC safety manager same day; corrective briefing documented RESOLVED
South yard material staging encroaching on drainage swale — recommend relocation before next rain event OPEN
BuildBrief · Weekly Progress Report · Week 24 · SAMPLE

Your Archive — Always On

24Weeks Captured
1,392Photos Filed
6Films Delivered
100%Date-Stamped

Notes for the Owner

Project remains ahead of the baseline schedule by approximately one week. Tuesday's lightning hold cost 4 hours; recovered with Thursday's extended shift at no premium cost. No budget flags this week. Next capture: Tuesday, August 18.
This lands in your inbox every Friday.  Start with a one-month pilot — four captures, four reports, one executive video.
Demonstration report with representative content. No affiliation with any actual project or contractor is implied. Demo photos and video use licensed stock imagery (Unsplash / Pexels).

Want reports like this for your sites?

Start with a one-month pilot — four captures, four reports, one executive video — then decide.

Book Your Pilot Month — $2,500

Questions? Call (321) 710-9671 or email hello@getbuildbrief.com